Summary
DOTD will shut down the road near the Patoutville bridge for about 90 days starting in the next month or two, meaning travelers to Weeks Island must detour through Glencoe.
At a glance
- Total mentions
- 4
- Last 30 days
- 1
Discussed at 2 meetings in the last 60 days; most recently Oct 28, 2026.
Impact analysis
Motorists benefit long-term from repaired roads, though the repair period brings inconvenience.
Residents and farmers traveling to Weeks Island and the Point will face a lengthy detour for three months.
Mentions & discussions (4)
Parish Council — October 28, 2026
The road is closed for three months of repairs, and 18-wheelers can't turn around at the closure sign — Pellerin is working with DOTD to add warning signs at Highway 90.
Parish Council — October 14, 2026
Highway 83/Weeks Island Road shuts down completely around October 26 for about three months for a DOTD project. Officials plan to keep Cypremort (Petou) Landing open, but that could change.
Parish Council — March 25, 2026
DOTD will fully close Highway 83 near Patu Bayou starting around April 1 for a 3-4 month project raising the road and redoing ramps and the bridge. The boat landing stays open but you'll have to detour to reach it.
Parish Council — March 11, 2026
DOTD will shut down the road near the Patoutville bridge for about 90 days starting in the next month or two, meaning travelers to Weeks Island must detour through Glencoe.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Iberia Parish
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.